MOULDLKnowledge BaseElectrical Knowledge Base3D Model DownloadsMembership
中文版Model Store »
Knowledge Base › Electrical Knowledge Base › Three-phase insulation resistance test method and standard
HomeModels
Table of contents

On this page

Electrical & Electronic Basics (600 articles)

Quick Reference

  • PLC & Programming
  • Electrical & Electronic Basics (monthly)(每月更新中)
  • Electrical Control & Drawings (monthly)(每月更新中)
  • Drives & Actuators (monthly)(每月更新中)
  • Sensors & Detection (monthly)(每月更新中)
  • Industrial Communication & Networks (monthly)(每月更新中)
  • HMI & Host Systems (monthly)(每月更新中)
  • Industrial Robots & Motion Control (monthly)(每月更新中)
  • Mechatronic System Integration (monthly)(每月更新中)
  • Fault Diagnosis & Standards (monthly)(每月更新中)

Three-phase insulation resistance test method and standard

After new install or overhaul, insulation testing decides whether equipment will leak or arc. This page covers megger selection, three-phase winding test and the standard limits.

1. How it works

Use an insulation resistance tester, the megger, with voltage rated to the equipment: 500 V for low-voltage gear up to 500 V, 1000 or 2500 V for high voltage. Digital types with timed reading are steadier. The equipment must be de-energized and discharged; large capacitors like cables and motors need thorough discharge or they hurt you and read falsely low.

2. Practice and pitfalls

For a motor, test each phase to frame with the other two shorted to earth, line terminal on the winding and earth on the frame; the reading should exceed the rule, generally 0.5 megohm for low-voltage motors and 1 megohm for critical kit. Test between phases too, and cables between conductors and screen, transformers between windings and to earth.

3. Insulation test

ItemMethodStandard
Meter500V if 500higher if HV
To framephase-shell>=0.5 M
Between2 ph-othersame
AbsorbR60/R15>=1.3
Dischargethoroughsafe
Readtimeddigital

4. Notes

Insulation testing is the safety gate before energizing; do it on new, damp, idle or overhauled equipment and log trends so a sudden drop flags latent fault. Do not scrap on a low damp reading, dry and retest. Use the right megger voltage and wiring, and discharge properly afterward.

5. References

The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Commissioning follows GB/T 50150 and machine safety IEC 60204-1. Always check the device datasheet and the product design file for ratings and derating.

6. Cautions

⚠️ Three common pitfalls:
① Testing before discharge hurts from residual cap and reads low
② A low-voltage megger on HV gear misses insulation defects
③ Scrapping on a damp low reading skips the dry retest

Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.