Temporary power kills more electricians than permanent installations, because the wiring looks provisional and nobody owns it. This page sets out the three level distribution scheme, the one machine one breaker rule, and the box requirements.
Site power follows a three level chain: a main distribution box at the incomer, distribution boxes per zone, and a switch box at each machine. The main box carries a total isolator plus a 300 mA delayed RCD for fire protection; zone boxes carry isolation and short circuit protection per outgoing way, rated IP44 and above against rain; every machine gets its own switch box with a 30 mA instantaneous RCD and a load side isolator, one machine, one switch, one RCD, one box. A single breaker feeding several machines through daisy chained plugs is the classic site violation.
Cables run as tough rubber sheathed flexible cord on insulators or overhead, never bare twisted wire or aluminum light cord across walkways, and never pinned under steel plates where forklifts chew them. Damp and metal confined work uses 24 or 12 V lighting through a safety isolator. Boxes sit on stands, doors lock, and a weekly inspection with recorded results is the minimum. Temporary does not mean unmanaged: every temporary circuit gets an approval, a responsible person and an expiry date.
| Level | Configuration | Requirement |
|---|---|---|
| Main distribution box | Total isolator plus 300mA RCD | Time delayed type |
| Zone distribution box | Per way isolation and short circuit | Rainproof IP44 |
| Machine switch box | 30mA final RCD | One machine one switch |
| Cables | Tough rubber sheathed cord | No twisted or aluminum wire |
| Lighting | 24 or 12V safety supply | For damp locations |
Build the three level chain with one machine per switch box and a 30 mA final RCD, run only sheathed cable, use safety voltage lamps in damp work, and lock every box.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Construction site temporary power follows JGJ 46, low voltage distribution GB 50054, with machinery safety per GB/T 5226.1 and IEC 60204-1. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.