Repeated earthing is the last line of defence in a TN system - it caps fault voltage and saves the day when the neutral breaks. This page covers where to install it, what resistance to demand, and how to test honestly.
Repeated earthing means connecting the PEN or PE conductor to earth not only at the transformer neutral but along the route. It lowers touch voltage during a frame fault, stabilizes the neutral if the PEN breaks (preventing phase-voltage excursions), and evens out potential during lightning induction. Required locations: every kilometre or so on overhead mains, at cable terminations, at building entries, and wherever PEN splits into PE and N.
Values: a single repeated earth electrode is generally ≤10Ω, parallel with the 4Ω working earth of the transformer. Measure with a three-pole earth tester (auxiliary electrodes 5 to 10m away) or a clamp-type tester; wet-soil readings run low, dry season high - allow seasonal margin. Workmanship traps: water pipes are forbidden as the sole electrode (plastic sections break the path), welded lap joints must meet the code (flat steel twice its width, round steel six times its diameter), and bolted terminals need anti-loosening hardware. Number, archive and retest every earthing point before each storm season.
| Earthing type | Resistance limit | Test method | Interval |
|---|---|---|---|
| Transformer working earth | ≤4Ω | Three-pole fall-of-potential | Yearly |
| Repeated earth (single) | ≤10Ω | Three-pole or clamp | Yearly, pre-storm |
| TT protective earth | RA × IΔn ≤ 50V | Three-pole | Yearly |
| Lightning protection | 1~30Ω by class | Three-pole | Pre-storm season |
| Data room combined | ≤1Ω (when specified) | Three-pole | Yearly |
| ESD earthing | ≤100Ω | Earth tester | As required |
Checklist: earth at building entry, at the PEN split and at line ends; test all points before storm season and file the numbers; weld laps to code and lock bolted terminals. Water pipes are not a plan.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Earthing design per GB/T 50065; installation and acceptance of earthing per GB 50169. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.