Sizing a generator on average power leaves it unable to start a motor; sizing a breaker on running current means a trip at every start. This page puts numbers on the starting surge.
Average power is what the energy meter bills; peak power decides whether equipment survives and whether protection nuisance-trips. A motor is the extreme case: direct-on-line starting draws 6 to 7 times rated current at a power factor of 0.3 to 0.4, so apparent power peaks 4 to 5 times steady state. A 7.5kW motor jumps from about 9kVA running to roughly 66kVA at start - for half a second to a few seconds, but every generator, UPS, breaker and cable must live through it.
Sizing rules: generators need 2.5 to 3 times motor rating or the voltage dip releases the contactors; UPS units need industrial overload ratings or generous oversizing; breakers need the D-curve (10 to 20 times) for motor circuits since a C-curve sits on the edge of the inrush; long cables need a voltage-drop check because dips beyond 15 percent make contactors chatter. Cures: VFD starting cuts current to 1.5 times and halves generator sizing; soft starters limit to 2 to 4 times; stagger multiple large motors 5 to 10 seconds apart.
| Starting method | Current multiple | Peak S vs running | Requirements |
|---|---|---|---|
| Direct on line | 6~7x | About 4~5x | 3x generator, D-curve breaker |
| Star-delta | 2~2.5x | About 2x | Mind the torque |
| Autotransformer | 3~4x | About 2.5x | Classic for large motors |
| Soft starter | 2~4x adjustable | About 1.5~2x | Bypass contactor needed |
| VFD | 1~1.5x | About 1.2x | Best sizing, highest cost |
| Sequential starts | One at a time | Size on the largest | 5~10s stagger logic |
Checklist: generators at three times motor load, UPS margin per starting method, breaker instantaneous 20 percent above the inrush peak, and a voltage-drop check on long runs. If the peak is not covered, the average is irrelevant.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Motor starting performance per GB/T 755; breaker trip characteristics per GB/T 14048.2; plant supply per GB/T 5226.1. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.