MOULDLKnowledge BaseElectrical Knowledge Base3D Model DownloadsMembership
中文版Model Store »
Knowledge Base › Electrical Knowledge Base › SPD parameters: nominal and maximum discharge current explained
HomeModels
Table of contents

On this page

Electrical & Electronic Basics (698 articles)

Quick Reference

  • PLC & Programming
  • Electrical & Electronic Basics (monthly)(每月更新中)
  • Electrical Control & Drawings (monthly)(每月更新中)
  • Drives & Actuators (monthly)(每月更新中)
  • Sensors & Detection (monthly)(每月更新中)
  • Industrial Communication & Networks (monthly)(每月更新中)
  • HMI & Host Systems (monthly)(每月更新中)
  • Industrial Robots & Motion Control (monthly)(每月更新中)
  • Mechatronic System Integration (monthly)(每月更新中)
  • Fault Diagnosis & Standards (monthly)(每月更新中)

SPD parameters: nominal and maximum discharge current explained

What do In, Imax and Up on a surge protective device really mean? This page defines the key parameters, walks the coordinated multi-level installation, and shows how to verify the energy coordination.

1. How it works

In is the nominal discharge current on an 8/20 µs wave that the SPD survives 15 times, representing sustained capability; Imax is the single-shot maximum on the same wave, usually 2 to 2.5 times In. Up is the voltage protection level, the residual voltage across the SPD under impulse, which must sit below the protected equipment impulse withstand Uw, practically Up ≤ 0.8Uw. Uc is the maximum continuous operating voltage, typically 275 V on a 220/380 V system, with 253 V acceptable on clean TN supplies but 275 V the safe choice where harmonics abound.

2. Numbers and practice

Grade the installation by lightning protection zone: class I test at the main board on the LPZ0 to LPZ1 boundary uses 10/350 µs impulse current Iimp of 12.5 to 25 kA per phase to dump the direct-strike energy; class II at sub-boards takes In of 20 to 40 kA on 8/20 µs; class III at the equipment takes 5 to 10 kA with lower Up. Coordination needs at least 10 m of cable between stages, otherwise a decoupling inductor, so the upstream stage fires first. Every SPD needs backup overcurrent protection, usually 63 to 125 A per the maker, so a shorted unit cannot set the board on fire.

3. Pitfalls and fixes

Selection runs: fix the building lightning class and zone boundaries, take the minimum In or Iimp from the tables, check equipment impulse withstand of 1.5 to 2.5 kV for electronics and 4 kV for distribution gear against Up, choose the connection scheme for the earthing system such as four-mode or 3+1, and add another stage when the run to the equipment exceeds 10 m. Inspect the status windows, wire the remote contact into monitoring, and survey before each storm season.

4. SPD staging parameters

StageLocationWave or parameterTypical value
First stageMain boardIimp 10/350 µs12.5~25 kA per phase
Second stageSub-distributionIn 8/20 µs20~40 kA
Third stageBefore equipmentIn 8/20 µs5~10 kA
Uc choiceTN systemContinuous voltage275 V safe
Up checkEquipment endResidual coordination≤ 0.8Uw
Backup protectionUpstream of SPDFuse or breaker63~125 A

5. Notes

Survey every SPD before storm season: status windows, remote signalling, bonding continuity. Replace failed modules with the same type and batch, and after installation verify the coordination by measuring residual voltage stage by stage, so the second level is not just decoration.

6. References

The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: See GB/T 18802.1 (IEC 61643-11) for surge protective devices and GB 50057 for lightning protection design. Always check the device datasheet and the product design file for ratings and derating.

7. Cautions

⚠️ Three common pitfalls:
① Substituting a class II 8/20 µs unit for the class I Iimp stage: direct-strike energy blows the SPD apart and scorches the busbars
② Two SPD stages closer than 10 m without a decoupling inductor: both fire together and the fine second stage takes the whole hit
③ Omitting the backup fuse ahead of the SPD: an aged MOV shorts, heats and starts cabinet fires

Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.