MOULDLKnowledge BaseElectrical Knowledge Base3D Model DownloadsMembership
中文版Model Store »
Knowledge Base › Electrical Knowledge Base › Auxiliary contacts, shunt and undervoltage releases on circuit breakers
HomeModels
Table of contents

On this page

Electrical & Electronic Basics (698 articles)

Quick Reference

  • PLC & Programming
  • Electrical & Electronic Basics (monthly)(每月更新中)
  • Electrical Control & Drawings (monthly)(每月更新中)
  • Drives & Actuators (monthly)(每月更新中)
  • Sensors & Detection (monthly)(每月更新中)
  • Industrial Communication & Networks (monthly)(每月更新中)
  • HMI & Host Systems (monthly)(每月更新中)
  • Industrial Robots & Motion Control (monthly)(每月更新中)
  • Mechatronic System Integration (monthly)(每月更新中)
  • Fault Diagnosis & Standards (monthly)(每月更新中)

Auxiliary contacts, shunt and undervoltage releases on circuit breakers

Beyond the main contacts, a breaker carries a row of small terminals: auxiliaries, shunt trip, undervoltage release. This page explains what each does, how to wire them, and classic interlock applications for control design.

1. How it works

Auxiliary contacts move with the main contacts, typically 2 to 4 NO and NC pairs rated 3 to 6 A, feeding breaker status to the control system: closed indication, trip alarm, spring charged, racking position. A common block locks the closing circuit until spring charging completes. Mind the small rating: drive contactor coils through an interposing relay, never directly from an auxiliary contact.

2. Numbers and practice

The shunt release is a short-time coil that trips the breaker within 0.05 to 0.3 s of energising, used for remote tripping and fire-alarm power shedding at AC 220 V or DC 110/220 V; energising beyond about 1 s burns the coil unless the type has self-cut. The undervoltage release works the other way, tripping when voltage falls below 35 to 70 percent of rated, and needs continuous energisation, so a blown fuse in its voltage circuit trips the whole board, a classic cascade-avoidance trap.

3. Pitfalls and fixes

Interlock examples: bus-tie versus two incomers electrically blocked against paralleling; fire alarm in series with shunt trips of non-fire feeders; transformer room door switch in the undervoltage circuit so opening the door kills the board. Test shunt releases yearly in the TEST position between 70 and 110 percent of rated voltage, check undervoltage trips below 35 percent, and verify auxiliary contact agreement with the main contacts with a meter, since a poor contact breeds false alarms.

4. Breaker accessories at a glance

AccessoryOperating conditionTypical useCaution
Auxiliary contactsMove with main contactsStatus, indication, PLC input3~6 A, use interposer
Shunt releasePulse energise to tripRemote trip, fire sheddingShort-time, no sustained feed
Undervoltage releaseBelow 35~70% voltageLoss-of-voltage protectionNeeds continuous supply
Charged-spring contactSpring fully chargedBlocks closing until readyRequired for motorised units
Alarm contactTrip-unit fault flagSeparates faults from normal openWire to alarm system
Racking position switchService/test/isolatedPosition interlock and monitoringNo closing unless home

5. Notes

Draw the accessory wiring with terminal numbers before building the panel and match coil voltage classes to the control supply. Put accessory operation in the annual test list and log operating voltages to trend degradation.

6. References

The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: See GB/T 14048.2 for breaker accessories and IEC 60204-1 for control circuit design. Always check the device datasheet and the product design file for ratings and derating.

7. Cautions

⚠️ Three common pitfalls:
① Holding the shunt release energised: the coil is short-time rated and burns past one second, so pulse it through a contact
② Overlooking the undervoltage release fuse: one drop-out trips the whole board, so monitor the voltage circuit
③ Driving a contactor coil straight from an auxiliary contact: 3 to 6 A contacts weld and the status readings all lie

Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.