Where should an RCD sit, how does the neutral wire in, and why does it trip constantly? This page covers graded installation, wiring rules and a four-step nuisance-trip diagnosis.
Grade the protection from the end: 30 mA fast types on final socket circuits for personal protection, 100 to 300 mA delayed types mid-distribution for fire protection with at least 0.15 s of grading, and 300 to 500 mA at the incomer for fire only, if at all. Fire-fighting circuits carry monitoring-only residual current devices so the pump never loses supply. Hand-held tools and wet locations such as bathrooms and outdoor sockets mandatorily take 30 mA.
Wiring rules: each RCD owns its load-side neutral exclusively, shared neutrals or repeated earthing downstream upset the zero-sequence balance and cause constant trips; phases and neutral pass through the same window in the same direction; the PE never passes through the toroid. The classic faults are two devices sharing one neutral, a load-side neutral earthed to a rod, and a single-phase load wired across the wrong poles of a four-pole unit.
Diagnose trips in four steps: distinguish real leakage from nuisance by whether it trips immediately on closing; switch everything off and re-energise circuit by circuit until the culprit appears; measure leakage on the PE bar with a milliamp meter, allowing 1 to 3 mA per electronic appliance and investigating any circuit beyond 30 mA; and inspect the neutral for repeated earthing or sharing. Wet-season trips usually mean damp insulation below 0.5 MΩ that needs drying or rewiring.
| Level | Rated residual current | Trip time | Protects |
|---|---|---|---|
| Final sockets | 30 mA | Within 0.1 s | People |
| Mid-distribution | 100~300 mA | 0.15~0.3 s | Fire, grading |
| Incomer | 300~500 mA | Delayed | Fire only |
| Fire circuits | Monitor, no trip | None | Keeps pumps alive |
| Hand tools | 30 mA | Within 0.1 s | Mandatory |
| Wet locations | 30 mA | Within 0.1 s | Mandatory |
Press the test button monthly with a log, and yearly measure actual trip current and time within ±10 percent of rating. Commission new RCDs with a full leakage survey first, so the first week is not a war of repeated trips.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: See GB/T 6829 and GB 13955 for RCD requirements and installation, with IEC 60204-1 for machinery. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.